We have the following questions re T/G units from the Philippines; please clarify as soon as possible.
1. Please quote USD CIF Manila
A: at this time we provide FOB price.
2. Difference between Impulse Turbine & Francis Turbine
A:The design head is 96.7m,so Francis type is much more economical than Impulse.
3. Can this hydraulic turbine generate 12MW at 96.7M Net Head?
A:at 96.7M Net Head, the design flow is 13.874m3 /s, the turbine’s efficiency is 94% with capacity at 12.371MW; generator efficiency is 97% with capacity at 12mw. 4. Who is the turbine manufacturer & can you arrange an inspection visit?
A: turbine manufacturer: CHONGQING WATER TURBINE WORKS CO. LTD(CWTW), and you are welcome to inspect our facility.
5. Who is the generator manufacturer & can you also arrange an inspection visit? A:Generator: CHONGQING WATER TURBINE WORKS CO. LTD(CWTW), and you are welcome to inspect our facility.
6. Will your generator operate at 60HZ? A�?60Hz�?/DIV>
7. Is your main valve butterfly type? A�?(Hydraulic control butterfly valve with accumulator)
8. Does your price for the governor includes oil pressure device? A:governor and oil pressure device assembled together, oil pressure device’s price is include in Governor price.
9. Does your price for instrument unit include automation component? A�?automation component is listed in Automatization
10.What is the delivery period of T/G unit? A: please refer to the following:
Project Time Schedule for 2x12MW
Hydro Power Plant in Turkey
1. 30 days after the contract effectiveness, civil excavation drawings.
2. 60 days after contract effectiveness, providing drawings for discussion which is to be hold in ten days.
3. 90 days after contract effectiveness, providing drawings for second discussion which is to be hold in ten days.
4. 150 days after contract effectiveness, providing embedded parts for the first phase.
5. 300 days after contract effectiveness, providing hydro turbine (excluding the rotating parts).
6. 360 days after contract effectiveness, providing main valves, and generator stators, lower Bracket.
7. within 420 days, other balance equipments.
These are the preliminary schedule, which should be finally fixed to situation.
|